DayDateNameDescription

Tue

September 7, 2021
Preparing for craning back to land

All the equipment we don't use will be craned back to the land. We need to prepare for lifting.

Wed

September 8, 2021
Moving back to land. Moving the unused materials back to Tsuen Wan. Cleaning the racks. 11:00 is t

Lifting equipment, at high tide. Driving back to Tsuen Wan. organizing the materials in the racks in Tsuen Wan

Thu

September 9, 2021
Compression belts, bollards on deck, towing rope,

Preparing the platform for towing

Fri

September 10, 2021
Prefabrication of construction modules. Roof skirt. Lower deck skirt. Triangles.

Typhoon 2 - likely. Lighting, electronics

Sat

September 11, 2021
Prefabrication of construction modules. Triangles

Typhoon 3 - likely. Lighting, electronics

Sun

September 12, 2021
Prefabrication of construction modules. Lighting and biology equipments

Typhoon 2 - likely. Biology equipment production

Mon

September 13, 2021
Towing from Sai Kung to North Point, installing sinkers

Probably safer to tow that day

Tue

September 14, 2021
Bamboo works day 1

Vertical Columns, Diagonal triangulation. Repairs of towing.

Wed

September 15, 2021

Thu

September 16, 2021
Bamboo works day 2

Bamboo roof structure

Fri

September 17, 2021
Roofing

Polycarbonate roof

Sat

September 18, 2021
Walls

Roof edge with corrugated steel sheets. Below deck edge with corrugated steel sheets.

Sun

September 19, 2021
Final touches of paint

Artwork operational with lights, safety features etc

Monday

September 20, 2021
Dry, ready to visit

Opening